Projects

Inland Rail (Parkes to Narrabri)

Civil Project Partners performed work on the first contract of Inland Rail, Parkes to Narromine section, with the InLink JV comprising of Fulton Hogan and BMD. A tender planner supplemented the team and was present throughout the tender period and also through the negotiation period. The Inlink JV was ultimately successful in securing the $310M contract assisted by the ability for the tender team to understand the methodologies, time-frames and resource allocations using the expertise of our planner applying our P6 and TILOS software tools.

parkes-narromine

Project information

Project Owner
ARTC
Client
Inlink JV (Fulton Hogan & BMD)
Stage
Tender
Location
Parkes to Narrabri, NSW
Capital Cost
$310M
Year
2018
Outcome
Successful

Scope

  • 5.3 km of new rail
  • 97 km of track upgrade
    • Lime stabilisation works
    • Earthworks for embankment
    • Capping and ballast
    • Rail
  • Level crossing upgrades

Service Provided

  • Planner seconded into the InLink JV team to plan the tender program
  • Gant chart in P6
  • Time-chainage program using TILOS
  • Resource optimising through the use of programming software tools
  • Planner continued to support delivery team after award

 