Coomera Connector – Stage 1 Central

The Coomera Connector Project is part of the Pacific Motorway M1 Upgrade Program, broken down into two stages.

The project will relieve congestion and safety issues along with queuing along interchanges. Connections for local traffic will be improved to access northern Gold Coast regions, rather than impeding the M1, thus improving travel times along the Pacific Motorway.

Stage 1 Central includes the section between Helensvale Road to Smith Street Motorway, Molendinar.

Image sourced from project page on the Department of Transport and Main Roads.

Project information

Project Owner
Transport and Main Roads
Client
C2C (CPB, SEE Civil, GHD, SMEC consortium)
Stage
Design and Construction Tender
Location
Coomera, Gold Coast
Capital Cost
~$1B
Year
2022
Outcome
Shortlisted

Scope

Civil Project Partners scope of works included duplication of the M1 for the ‘Coomera Connector’ between Helensvale Road and Smith Street Motorway.
Items included:
  • 24 bridges
  • RSS walls
  • Two carriageways of 2-lanes each over 9km in length

Service Provided

Civil Project Partners were engaged to provide support to the client with a Senior Planner working within the team. Services included 4d planning on critical infrastructure for staging.
Deliverables included:
  • Tender Program for design and construction
  • Resource load program to develop procurement strategies.
  • Explore scenario programming for optimisation.

Tools used